Elderslie Street

Scope of Works -   Lift Pit Waterproofing
Date - January 2020
Summary 
A brickwork constructed lift pit experiencing water ingress to the point where continual sub-pump water removal was required.

An attempt at repair with a brush on, fast set application, failed. We were asked to attend site to resolve with the Sika 1 Tanking system.

All existing applications removed, Pit prepared by vacuum extracted grinding, water controlled with relief pipes and Sika application applied to an epoxy bonding aid. Existing fixtures mastic sealed in process.

Pit now dry for equipment installation by others.